gadj1976 wrote: There is. She too gave birth on his chest.
Nope - once is enough for that kind of shock.
by Psyber » Sat May 31, 2014 5:15 pm
gadj1976 wrote: There is. She too gave birth on his chest.
by Spargo » Wed Jun 04, 2014 12:45 pm
by bennymacca » Wed Jun 04, 2014 12:57 pm
Spargo wrote:Does bennymacca get paid per post?
by Spargo » Wed Jun 04, 2014 1:04 pm
bennymacca wrote:Spargo wrote:Does bennymacca get paid per post?
i wish. prolly the only way i could be a millionaire too
but no, im just a forum whore, and unfortunately for SA footy, some of the other forums that i have been on have been shut down or just are dying a slow death.
by nuggety goodness » Fri Jun 06, 2014 12:37 am
by mighty_tiger_79 » Fri Jun 06, 2014 7:50 am
by smac » Fri Jun 06, 2014 8:50 am
nuggety goodness wrote:Is it worth me buying a scooter for the work commute? Has anyone got one or did do once?
$1500 for a 50cc so I don't need a bike license
cheap to run, $20/Mth rego, and about $15/ fnight in fuel
Tossing it up... Thoughts?
by Kahuna » Fri Jun 06, 2014 8:59 am
nuggety goodness wrote:$1500 for a 50cc so I don't need a bike license
cheap to run, $20/Mth rego, and about $15/ fnight in fuel
Tossing it up... Thoughts?
by whufc » Fri Jun 06, 2014 9:12 pm
by smac » Fri Jun 06, 2014 9:54 pm
by whufc » Sat Jun 07, 2014 8:03 am
smac wrote:Can't fault it. Spent about $1500 on it for various tickets in December, never missed a beat.
by wristwatcher » Sat Jun 07, 2014 9:52 am
by heater31 » Sat Jun 07, 2014 10:00 am
wristwatcher wrote:Any tips for slowing my powerful over zealous sperm
by Mic » Sat Jun 07, 2014 10:02 am
whufc wrote:How reliable the website 'stub hub' is for getting tickets to American sporting events
by helicopterking » Sat Jun 07, 2014 2:02 pm
Sheik Yerbouti wrote:kickinit wrote:Jase wrote:Rookie question here...
We had a quote for some paving, retaining storm water for $11500 cash ... accepted the quote and had the work done, and the guy has come back and said we need to pay an extra $1200 for "variations". The thing is the dude who did the work is Mrs Jase's cousin.
My question is, if you accept the quote is that like a contract and that is all you have to pay...?
Sent from my XT925 using Tapatalk
Sure is. Sometimes those there is extra work that needs to be doe and isn't seen until your in the middle of job. In saying that though he should of stopped shown you the problem and given you another quote to fix it. A no time should he go a head and do extra work and expect you to pay extra on top of your quote.
That's about right ^. Was there anything on paper, eg prices for siteworks, retaining & paving itemised? Standard practice is that if a variation pops up it should be discussed & a price set for the works as the work is in progress.
Did the variation bill have the actual variations listed or just verbalized?
If working for a builder/ contractor variations are always on paper & signed off by all parties before the work progresses.
by helicopterking » Tue Jun 10, 2014 12:17 pm
helicopterking wrote:Sheik Yerbouti wrote:kickinit wrote:Jase wrote:Rookie question here...
We had a quote for some paving, retaining storm water for $11500 cash ... accepted the quote and had the work done, and the guy has come back and said we need to pay an extra $1200 for "variations". The thing is the dude who did the work is Mrs Jase's cousin.
My question is, if you accept the quote is that like a contract and that is all you have to pay...?
Sent from my XT925 using Tapatalk
Sure is. Sometimes those there is extra work that needs to be doe and isn't seen until your in the middle of job. In saying that though he should of stopped shown you the problem and given you another quote to fix it. A no time should he go a head and do extra work and expect you to pay extra on top of your quote.
That's about right ^. Was there anything on paper, eg prices for siteworks, retaining & paving itemised? Standard practice is that if a variation pops up it should be discussed & a price set for the works as the work is in progress.
Did the variation bill have the actual variations listed or just verbalized?
If working for a builder/ contractor variations are always on paper & signed off by all parties before the work progresses.
Just happened to me just then. Said he mis-calculated and under quoted on concrete after the job has been finished and expects me to pay an extra $1000 on top of the quote. He also said that it would all be done in 6 days. It's been 6 weeks. Not once was it discussed that it was going to cost any extra, and if he mis calculated, then bad luck.
by Phantom Gossiper » Tue Jun 10, 2014 12:20 pm
helicopterking wrote:Coming to "collect" his money today, really looking forward to it after work.
by helicopterking » Tue Jun 10, 2014 2:27 pm
Phantom Gossiper wrote:helicopterking wrote:Coming to "collect" his money today, really looking forward to it after work.
You're not going to pay it are you?!
by Spargo » Tue Jun 10, 2014 9:12 pm
helicopterking wrote:helicopterking wrote:Coming to "collect" his money today, really looking forward to it after work.
Competitions SANFL Official Site | Country Footy SA | Southern Football League | VFL Footy
Club Forums Snouts Louts | The Roost | Redlegs Forum |